| Project: |
CEL-SCI
Corporation |
| Location: |
Elkridge,
Maryland |
| Owner: |
CEL-SCI
Corporation |
| Design/Build: |
BE&K,
Inc. |
| Estimated
Completion Date: |
October,
2008 |
| Cost
of Project: |
$1,000,000 – 5,000,000 |
| Job
Description: |
Construction
for CEL-SCI’s new drug manufacturing facility is underway
and moving quickly. CEL-SCI is a biotechnology company that
will use the new building for the manufacturing of a new cancer
treatment drug. The building is rated BLS-3 and contains a
large clean room for a manufacturing area in which the drugs
will be produced and packaged. VarcoMac will provide new electrical
service, lighting, fire alarm, telecom, generators and a UPS
to support critical equipment.
An
official press release from CEL-SCI about the project can
be found here: http://www.cel-sci.com/press_9.html.
|
| What’s
Going On Now?: |
As
of March, VarcoMac has installed temporary power and is working
on feeders for the power distribution equipment. As the build-out
work within the existing structure progresses, VarcoMac will
begin their work to install the remaining electrical equipment.
Check back often for more updates.
|